PROGRESS WITH THE RE-BUILDING THE INTERIOR WALLS OF ST HUGH'S CHURCH
(IF YOU CLICK ON A PICTURE, A LARGE VIEW OF IT WILL OPEN IN A NEW WINDOW)
| PRIOR
TO WORK COMMENCING - THE INSIDE WALL SHOWING CRACKS |
|||
| 11
MAY 2003 - INSIDE WALL REMOVED (SOUTH SIDE) - NOTE STRUTS HOLDING UP
LINTELS |
|||
![]() |
|||
18
MAY 2003 - INSIDE WALL PARTIALLY REBUILT (SOUTH SIDE) |
![]() |
25 MAY 2003
- INSIDE WALL REBUILT (SOUTH SIDE) |
||
1 JUNE
2003 - INSIDE WALL REBUILT ( NORTH SIDE) |
||
8
JUNE 2003 - HEATERS RE-INSTALLED ON ALL WALLS, SEALING OF WALLS TO BUTRESSES STILL TO BE COMPLETED |
||
15
JUNE 2003 - SEALING OF WALLS TO BUTRESSES COMPLETED - CHURCH BACK TO
NORMAL. |
||