PROGRESS WITH THE RE-BUILDING THE INTERIOR WALLS OF ST HUGH'S CHURCH

(IF YOU CLICK ON A PICTURE, A LARGE VIEW OF IT WILL OPEN IN A NEW WINDOW)

PRIOR TO WORK COMMENCING - THE INSIDE WALL SHOWING CRACKS
                                       
11 MAY 2003 - INSIDE WALL REMOVED (SOUTH SIDE) - NOTE STRUTS HOLDING UP LINTELS
18 MAY 2003 - INSIDE WALL PARTIALLY REBUILT (SOUTH SIDE)

25 MAY 2003 - INSIDE WALL REBUILT (SOUTH SIDE)
WALL SECTION NEAREST ALTAR REBUILT (NORTH SIDE),
NEXT SECTION OF WALL PARTIALLY REMOVED (NORTH SIDE)

1 JUNE 2003 - INSIDE WALL REBUILT ( NORTH SIDE)
SEALING OF WALLS TO BUTRESSES TO BE COMPLETED
ESTIMATED COMPLETION DATE - FRIDAY 6 JUNE 2003

8 JUNE 2003 - HEATERS RE-INSTALLED ON ALL WALLS,
SEALING OF WALLS TO BUTRESSES STILL TO BE COMPLETED
15 JUNE 2003 - SEALING OF WALLS TO BUTRESSES COMPLETED - CHURCH BACK TO NORMAL.